I'm starting to think (new user) that it is not possible to copy entities from one layer and paste them in another.
I tried, no errors were indicated, and the positioning cursor appeared. Upon confirmation, the new layer appeared empty of content.
os: macos Catalina 10.15.7
qcad version: Community Edition 3.27.6.0 (3.27.6)
paste entities into other layer
Moderator: andrew
paste entities into other layer
Last edited by alex_r on Fri Jun 17, 2022 9:41 pm, edited 1 time in total.
Re: paste entities into other layer
By default, entities are pasted to their original layer.
You can choose "To current layer" in the options toolbar to paste to the current layer instead.
PS: please post to the correct forum for the QCAD Community Edition:
https://www.qcad.org/rsforum/viewforum.php?f=76
You can choose "To current layer" in the options toolbar to paste to the current layer instead.
PS: please post to the correct forum for the QCAD Community Edition:
https://www.qcad.org/rsforum/viewforum.php?f=76
Re: paste entities into other layer
Thanks. I have a follow-up question + will post it in CE topic.
Re: paste entities into other layer
I followed your advice. It worked, in part. Thanks!
One issue remains: upon pasting, block references present in the original layer are not pasted into the new destination layer.
What is the best approach to do such a thing, i.e., to copy all entities and blocks of an original layer, pasting them into another layer ?
Steps:
1. select all in original layer
2. activate destination layer
3. begin pasting
4. select "To current layer" option
5. ?
6. observe how current layer contains all that appeared in the original layer, block references included.
One issue remains: upon pasting, block references present in the original layer are not pasted into the new destination layer.
What is the best approach to do such a thing, i.e., to copy all entities and blocks of an original layer, pasting them into another layer ?
Steps:
1. select all in original layer
2. activate destination layer
3. begin pasting
4. select "To current layer" option
5. ?
6. observe how current layer contains all that appeared in the original layer, block references included.
Re: paste entities into other layer
Hi,
make sure a target layer is created.
On the source layer: Select all entities which have to be moved to an other layer,
then check the Property Editor below Generell Property's / Layer,
in the drop down menu you will find all existing layer - just chose the target layer. Done.
make sure the Property Editor is launched (Menu/View/Property Editor),
make sure a target layer is created.
On the source layer: Select all entities which have to be moved to an other layer,
then check the Property Editor below Generell Property's / Layer,
in the drop down menu you will find all existing layer - just chose the target layer. Done.
Work smart, not hard: QCad Pro
Win10/64, QcadPro, QcadCam version: Current.
If a thread is considered as "solved" please change the title of the first post to "[solved] Title..."
Win10/64, QcadPro, QcadCam version: Current.
If a thread is considered as "solved" please change the title of the first post to "[solved] Title..."
Re: paste entities into other layer
Hi,
In your list I miss the copy stage.
Otherwise you are pasting what is in the Clipboard in step 3.
A Block Reference is also an entity that will be copied/pasted like any other.
Working in Model Space, the entities that make up the Block Definition will remain on their creation layer.
These could be 'moved' to another layer while editing the Block in question itself.
To move a selection I usually double click on the destination layer (on the naming itself) in the Layer List.
To copy over I tend to duplicate (DP) before the double click.
Regards,
CVH
In your list I miss the copy stage.
Otherwise you are pasting what is in the Clipboard in step 3.
With "To current layer" all Clipboard entities are pasted in the current active layer.
A Block Reference is also an entity that will be copied/pasted like any other.
Working in Model Space, the entities that make up the Block Definition will remain on their creation layer.
These could be 'moved' to another layer while editing the Block in question itself.
To move a selection I usually double click on the destination layer (on the naming itself) in the Layer List.
To copy over I tend to duplicate (DP) before the double click.
Regards,
CVH
Last edited by CVH on Wed Jun 22, 2022 4:06 am, edited 1 time in total.
Re: paste entities into other layer
I haven't internalized yet the subtleties of working with model space, layer and blocks. I'm getting there, though.
Thanks!
Thanks!